Full explanation of the local control modes
Introduction
The SmartgridOne Controller has different control modes for the following types of devices:
- Storage, e.g. batteries
- Energy production devices, e.g. solar panels
- EV charging infrastructure
- Heat pumps, boilers & devices switched on/off by relay
Order of plans and priorities
When scheduling the devices with the same control mode, the following basic sequence is used in terms of planning:
- Heat pumps, boilers & devices switched on/off by relay. These devices are the least flexible to control.
- EV charging infrastructure. It is more efficient to consume your own energy immediately than to store it.
- Storage.
- Energy production devices, e.g. solar panels. Our own energy production is regulated last.
For the different possible control modes of the same device, the following order is used:
- Control not active, device always off and device always on.
- Control via API (if an external signal is active)
- Peakshaving / load balancing only
- Maximize self-consumption
- Cost optimisation
- Feed-in limitation to permissible feed-in limit
You can assign a priority to each device in its settings. The sequences outlined above are then used for all devices with the same priority. First, all the highest-priority devices are scheduled, then all high-priority devices, and so on.
To assign a priority to a device, see also Priorities.
By playing with the priorities, you can obtain a different order of scheduling if desired.
This means that if, for example, you give a higher priority to scheduling solar panels than batteries, the solar panels may be reregulated earlier than excess energy is stored in the batteries.
For heat pumps, boilers and on/off loads, the consumption is not known if they do not provide measurements or are not explicitly measured with a separate energy meter. As a result, the controller cannot distinguish this from the basic consumption of the building, and therefore cannot be taken into account in the priorities.
Application Example: Priority EV Charging Station
You have a parking lot with several EV charging stations. You want some charging stations to be given priority when charging for people who are often on the road. To do this, you can use the priorities and give priority to the EV charging stations.
Pricing parameters
Energy prices are used as the basis for all cost optimisations. The following formulas are used to convert market prices into your energy price:
Actual purchase price you pay for purchased energy = [Day ahead price in EUR/kWh] x [Buy energy cost scale factor] + [Buy energy cost scale offset in EUR/kWh] + [Buy grid cost]
Actual selling price you get for feed-in energy = [Day ahead price in EUR/kWh] x [Sell energy cost scale factor] + [Sell energy cost scale offset in EUR/kWh] – [Sell grid cost in EUR/kWh]
(Note the minus sign next to the grid costs of the energy fed in)
You can set these price parameters via the "Settings" tab of the app.
Grid costs
For grid costs, you enter the grid costs per kWh you pay. This is typically around 0.08 EUR/kWh for purchased energy. You can find this on your final energy bill or contract. For feed-in energy, this may vary:
If you have a reversing meter (Belgium) or if you are allowed to net (the Netherlands), the grid cost is the same for feed-in as for offtake.
Otherwise, you probably won't have to pay grid costs on feed-in energy. You then enter 0 in the grid costs for the energy that is fed in.
Scale factor on day ahead and fixed energy costs
The scale factor on the day-ahead price and the fixed cost for purchased and feed-in energy depend on your type of contract.
For a fixed and variable contract
The day ahead price does not play a role here. So, you need to set the vendor scaling factor to 0.
For "fixed cost of purchased energy in EUR/kWh" and "fixed cost of feed-in energy in EUR/kWh", enter respectively the price you pay to the supplier per kWh purchased and the price you receive from the supplier per kWh fed in.
If you have a reversing meter (Belgium) or if you are allowed to net (the Netherlands), the fixed costs for purchased and returned energy are the same.
For a dynamic contract
You can find the scale factor and fixed cost on your supplier's website or on your contract. Most suppliers work with a scale factor of 1, a fixed cost for purchase around 0.02 EUR/kWh and a fixed cost for feed-in around -0.02 EUR/kWh.
Current and Power limits
On the grid connection
In the SmartgridOne, you can set the current and power limits of the electrical installation. The SmartgridOne will take this into account when scheduling the controllable devices.
The current limit is used to monitor against overflowing. Please note, this is not a substitute for an electrical protection, but will ensure that your security will not trip unnecessarily. This limit is not intended to limit offtake and feed-in to the grid. To do this, use the power limits.
The power limits serve to indicate that only a limited amount of power from the grid may be taken from or fed back into the grid. You need to set these limits large enough, otherwise you run the risk that your devices will never be able to draw the power they need.
You can specify a safety margin to ensure that the maximum feed-in limit is never exceeded.
Please note, if you have an electric car, keep in mind that it needs at least 1500W if it is charging single-phase, or 4500W if it is charging three-phase. (Most electric cars require a minimum current of 6A or even 12A, and can temporarily malfunction until you plug it in again if the charging station is not allowed to provide it).
By groups
You can also use the groups page to indicate whether specific power limits apply to a group. These will also be included in the planning. To do this, enable advanced groups, and go to the settings of the group you want to apply the power limit to.
Three-phase connections
In the SmartgridOne, under "Settings" and → "Advanced settings", you can enable three-phase planning and monitoring.
Unless you absolutely need three-phase planning and monitoring due to, for example, a large imbalance in the phase currents, it is recommended to leave this option OFF. This is because this option requires you to also set which phases each device is connected to, and whether any phase mapping is required. This is prone to errors. This mapping is necessary to ensure that the current of a phase as measured by the energy meter actually corresponds to the current of a phase as reported by a device (it happens that the terminals L1, L2 and L3 of a device are not connected to the phases L1, L2 and L3 of the grid on a one-to-one basis, but for example extension L1 on network L2, extension L2 on network L1 and extension L3 on network L3).
If you leave the three-phase option off, the SmartgridOne will look internally at the most heavily loaded phase for current monitoring. In almost all cases, this is sufficient.
The three-phase option does not affect the power limits. Here, the SmartgridOne always look at the total power.
Storage
You can specify charging schedules to ensure that the storage has a certain charge percentage at fixed times on fixed days of the week. Please note that the SmartgridOne will try to follow the control mode in order to respect this charging schedule.
For more information, see Charging schedule batteries
Maximize self-consumption
In this mode, storage is used to cover as much self-consumption as possible with self-produced energy. The battery charges when energy would be fed back and discharges when energy would be drawn.
Self-consumption with (dis)charging at specific grid power thresholds
If you only want the battery to charge or discharge above or below a certain threshold, you can use the "Peakshaving only" strategy for this. Underlying this, the "Maximize self-consumption" and "Peakshaving only" strategies use the same algorithm, with all grid power thresholds set to zero for "Maximize self-consumption".
Peakshaving only
In this mode, storage is used to smooth out peaks. To do this, you enter the following thresholds for the grid power:
- Start discharge above (kW) (Discharge start): Above this grid power, the storage will discharge and the grid power will level off to this threshold.
- Stop discharging below (kW) (Discharge stop): When the storage is discharging, it will stop discharging as soon as the grid power drops below this threshold.
- Stop charging above (kW) (Charge stop): When the storage is charging, it will stop charging as soon as the grid power rises above this threshold.
- Start charging below (kW): Below this grid power, the storage will load and the grid power will level off to this threshold.

APPLICATION EXAMPLE 1
You have a grid connection that is limited to 100kW consumption. To avoid exceeding this power, you can, for example, use 80kW as a threshold value for starting and stopping discharging and 70kW for starting and stopping charging. As soon as the grid power rises above 80kW, the storage will discharge to limit the grid power to 80kW. At a later date when the grid power drops below 70kW, the storage is charged (resulting in a final grid power of 70kW).
APPLICATION EXAMPLE 2
Your installation falls under the system of the "terugdraaiende teller" (BE) / "salderen" (NL), but you have more solar generation than your grid connection can handle. You only want to charge your battery when there is more than 10kW of feed-in, and only have it discharged when you have more than 5 kW of consumption. To achieve this, you can set the thresholds "Start discharging above" and "Stop discharging below" to 5kW, and "Stop charging above" and "Start charging below" to -10kW. (minus 10kW).
Cost optimisation
In this mode, the storage charges at the cheapest possible times and discharges the storage to cover consumption at the most expensive times. The SmartgridOne takes into account:
- The energy prices, including differences between purchase and sale prices (charging your own solar energy is usually more interesting than charging from the grid).
- The predicted grid power.
- The efficiency of the battery.
- A minimum price difference between the cheap and expensive moments. You can use this to take into account, for example, the wear and tear when using the battery. See also Accounting for wear and tear costs, and battery efficiency.
Power Limit Monitoring
If necessary, the SmartgridOne will deploy the storage to prevent exceeding the power limits of the installation – regardless of the energy price at that time.
Energy trading
It is also possible to indicate that the storage may be used for energy trading. With this option, you can use the storage to buy energy at cheap times and sell it back at expensive times.